ConsMS is a construction contract-management application built on the Frappe Framework and designed to work with ERPNext business documents.
The current master branch focuses on the commercial and execution lifecycle of construction projects: Bills of Quantities (BOQs), tenders, contracts, mobilization, site measurements, progress claims / IPCs, variation orders, procurement linkage, invoicing linkage, budget tracking, profitability analysis, dashboards, and project workspace navigation.
This README documents the current
masterbranch. It is materially different from the older ConsMS codebase that focused mainly on daily site progress, labour, materials, equipment logs, repairs, and handover records.
Construction projects require commercial, project, procurement, site, and finance teams to work from the same contract quantities and values.
ConsMS is designed to provide that connection inside Frappe/ERPNext.
The application establishes a structured flow from:
Project / BOQ
↓
Tender
↓
Contract
↓
Mobilization
↓
Site Measurements
↓
Progress Claim / IPC
↓
Sales Invoice or Purchase Invoice
Variation Orders can adjust the commercial value during execution, while purchasing transactions can be linked to BOQ lines to support budget-versus-expenditure control.
| Business problem | ConsMS capability |
|---|---|
| Contract quantities and rates are maintained outside ERP | Structured Bills of Quantities with quantity, rate and amount calculations |
| Tender information is disconnected from awarded contracts | BOQ → Tender → Contract document mapping |
| Multiple contracts may accidentally be created for one tender | Backend validation enforces one active contract per tender |
| Contract mobilization is managed through spreadsheets or checklists | Configurable mobilization templates and site mobilization tracking |
| Site work measurement is difficult to reconcile with contract quantities | Site Measurement Logs reference BOQ items |
| Interim certificates are manually recalculated | Progress Claims calculate previous, current and cumulative quantities and values |
| Variations are disconnected from progress certification | Submitted variation orders are incorporated into progress claim calculations |
| Retention and certification calculations are spreadsheet-based | Progress Claim calculation logic includes retention, previous certification, VAT and net amount due |
| Construction purchasing cannot be compared cleanly to BOQ budgets | Procurement transaction items can carry BOQ and BOQ-line references |
| Management cannot easily see project commercial performance | BOQ Budget vs Expenditure and Contract Profitability reports |
| Construction processes are scattered across menus | Dedicated Construction MS workspace |
ConsMS is designed for organizations involved in project and contract-based construction operations, including:
- Main contractors
- Civil and infrastructure contractors
- Building contractors
- Engineering companies
- Quantity surveying teams
- Commercial and contracts departments
- Project managers
- Site engineers
- Procurement teams
- Finance teams handling progress billing
- Organizations already using ERPNext for Projects, Buying, Selling and Accounts
The current codebase should not automatically be treated as a complete replacement for every specialist construction platform.
Additional development or validation may be required for:
- tender evaluation and bid comparison
- subcontractor tendering
- advanced cost-code structures
- resource scheduling
- daily labour attendance
- plant fleet maintenance
- quality inspections
- HSE management
- document transmittals
- RFIs
- drawings and revision control
- extension-of-time claims
- liquidated damages
- defects liability management
- project cash-flow forecasting
- earned value management
- mobile offline site capture
DocType: BF Bill of Quantities
The BOQ provides the commercial baseline for the project.
Supported behavior includes:
- Project linkage
- BOQ line items
- quantity
- UOM
- unit rate
- line amount
- automatic BOQ total calculation
- import support
- submit / cancel / amend lifecycle
- creation of Material Request
- creation of Tender
- lookup of BOQ line items for downstream transactions
The BOQ controller recalculates each line as:
Amount = Quantity × Unit Rate
and aggregates the total BOQ value.
DocType: BF Tender
Tenders can be generated from a BOQ.
The current application supports a controlled BOQ-to-contract path:
BOQ → Tender → Contract
The backend prevents more than one active contract from being created for the same Tender.
Cancelled contracts are excluded from this restriction.
When a Contract is created from a Tender, the application can populate required contract submittals using configured BF Document Type records.
This provides a starting checklist for documents required during contract execution.
DocType: BF Contract
Contracts support both:
- Main Contract
- Subcontract
A Main Contract can reference:
- Tender
- Project
- Client / Customer
- BOQ
- Contract amount
- Contingency percentage
- Contingency amount
- Retention percentage
- Total contract value
- Required submittals
Subcontracts can reference:
- Parent Main Contract
- Supplier / Subcontractor
This provides the basis for relating subcontractor commercial activity to the main contract.
The application calculates:
Contingency Amount = Contract Amount × Contingency %
Total Contract Value = Contract Amount + Contingency Amount
If contingency exceeds 15%, the application displays a warning for review.
From a Contract, users can create:
- Site Mobilization
- Variation Order
- Progress Claim
Site mobilization provides a checklist-based mechanism for ensuring the project is ready for execution.
The application supports mobilization statuses such as:
- Not Started
- In Progress
- Completed
The status is calculated from checklist items.
A Site Mobilization document cannot be submitted until all mobilization tasks are completed.
This provides a business control preventing formal mobilization closure while outstanding tasks remain.
DocTypes:
BF Mobilization TemplateBF Mobilization Template TaskBF Mobilization Task
Templates allow organizations to standardize recurring mobilization requirements.
Typical business uses may include:
- site possession
- insurance documentation
- permits
- temporary utilities
- site offices
- safety setup
- equipment mobilization
- statutory documents
- staff deployment
Actual template content is configurable by the organization.
Site Measurement Logs are used to capture measured work against BOQ items.
The application supports:
- Contract linkage
- BOQ-based item selection
- measurement items
- retrieval of BOQ descriptions and UOM
- controlled BOQ-item lookup
These measurements feed the progress-claim process.
Progress Claims are one of the main commercial controls in ConsMS.
A claim can be generated from a Contract.
The current logic supports:
- Claim period
- BOQ claim items
- Previous quantity
- This-period quantity
- Cumulative quantity
- Unit rate
- This-period value
- Cumulative value
- Materials on site
- Approved variations
- Retention
- Advance payment recovery
- Previous certified amount
- Net amount due
- VAT
- Total amount certified
The Progress Claim can fetch submitted Site Measurement Logs for a selected period.
The application:
- Loads the Contract BOQ.
- Retrieves BOQ items.
- Finds submitted Site Measurement Logs for the Contract and claim period.
- Aggregates measured quantities.
- Retrieves quantities already claimed in earlier submitted claims.
- Calculates current and cumulative quantities.
- Retrieves approved Variation Orders.
- Calculates previous variation certification.
- Calculates the resulting claim values.
This creates a direct operational link:
BOQ
↓
Site Measurement
↓
Progress Claim / IPC
The application prevents:
Period Frombeing later thanPeriod To- overlapping active Progress Claim periods for the same Contract
This reduces duplicate certification periods.
For each Variation Order:
Cumulative Variation Claim
=
Previously Certified
+
This Period Amount
The application prevents cumulative claimed value from exceeding the approved/requested variation amount.
The application calculates values approximately as follows:
This Period Work Value
=
This Period Quantity × Unit Rate
Cumulative Quantity
=
Previous Quantity + This Period Quantity
Cumulative Work Value
=
Cumulative Quantity × Unit Rate
Gross Valuation
=
Work Executed
+ Approved Variations
+ Materials on Site
Retention Deduction
=
Gross Valuation × Retention %
Net Amount Due
=
Gross Valuation
- Retention
- Advance Recovery
- Previous Certified Amount
VAT
=
Net Amount Due × VAT %
Total Amount Certified
=
Net Amount Due + VAT
The Progress Claim controller includes mappings for:
- Sales Invoice
- Purchase Invoice
A Progress Claim can generate a Sales Invoice conceptually linked to:
- Project
- Construction Contract
- Progress Claim
A Progress Claim can also generate a Purchase Invoice for subcontractor-side certification.
The default invoice item is read from BF Construction Settings.
Deployment note: the current
masterbranch contains intended Sales Invoice custom-field definitions inconsms/custom_fields.py, buthooks.pyassignsafter_migratetwice. In Python, the later assignment takes precedence. The active hook currently points toconsms.setup.after_migrate. Deployments should verify the intended invoice linkage fields exist before relying on invoice generation.
Variation Orders provide structured control of additions or changes to contract scope.
They support:
- Project
- Contract
- Variation items
- Quantity
- Unit rate
- Amount
- Requested amount
- Reason / justification
- submit / cancel / amend lifecycle
The requested amount is calculated automatically from the variation lines.
Variation Orders are also incorporated into Progress Claim calculations.
The application extends ERPNext procurement documents to support BOQ linkage.
The active consms.setup.after_migrate routine creates BOQ fields on:
- Material Request
- Purchase Order
- Purchase Receipt
- Purchase Invoice
- Material Request Item
- Purchase Order Item
- Purchase Receipt Item
- Purchase Invoice Item
Child rows can reference:
- BF Bill of Quantities
- BF BOQ Item
- BOQ Item ID
This establishes the basis for tracing procurement commitments and expenditures back to individual BOQ lines.
The app includes custom JavaScript for Material Request and extends the Material Request dashboard.
A BOQ can generate a Material Request with:
- Purchase request type
- Project
- BOQ reference
The Material Request dashboard also receives a Construction section linking back to the BOQ.
Report: BOQ Budget vs Expenditure
The report compares each BOQ line against ERPNext procurement values.
It includes:
- BOQ
- Project
- BOQ Item
- Description
- UOM
- Budget Quantity
- Unit Rate
- Budget Amount
- Committed Cost from submitted Purchase Orders
- Actual Spend from submitted Purchase Invoices
- Remaining Budget
- Utilization %
This provides a construction-specific view of:
BOQ Budget
vs
Purchase Commitment
vs
Actual Purchase Cost
Report: BF Contract Profitability
For submitted Main Contracts, the report calculates:
- Base Contract Value
- Submitted Variations
- Revised Contract Value
- Client Billing
- Subcontractor Costs
- Estimated Profit
- Actual Profit to Date
- Actual Margin %
The report derives client billing from submitted Sales Invoices linked to the Contract.
Subcontractor cost is derived from submitted Purchase Invoices linked either to:
- the Main Contract, or
- submitted Subcontracts belonging to that Main Contract
This creates a high-level commercial performance view by Contract.
The repository also includes a Variation vs Budget Report definition for construction variance visibility.
Review its final business logic against the organization's reporting requirements before production rollout.
The app includes a public Construction MS workspace.
It groups functionality into:
- Bill of Quantities
- Tenders
- Contracts
- Mobilization
- Variation Orders
- Measurement Logs
- Progress Claims (IPC)
- Document Types
- Mobilization Templates
- Construction Settings
The workspace also includes construction dashboard content such as Monthly Contract Awards.
The repository contains dashboard resources including:
- Monthly Contract Awards
- Submittal Approval Rate
- Active Tenders
- Pending Submittals
- Total Awarded Contracts
- Total Variation Value
These provide management-level visibility directly from the Construction workspace.
Contracts contain a submittal table.
Configured BF Document Type records can be automatically copied into newly created contracts as required submittals.
This can support tracking of required contract documentation such as:
- insurance documents
- drawings
- method statements
- bonds
- permits
- material approvals
- certificates
The exact document types are organization-configurable.
The repository includes a print format:
FIDIC IPC Certificate
This indicates an intended construction certification workflow aligned with interim payment certificate usage.
The presence of the print format should not be interpreted as legal or contractual compliance with every FIDIC contract form; each deployment should validate terminology, deductions, taxes and certificate format against the actual contract.
DocType: BF Construction Settings
The application includes construction-level configuration.
One known use is the default Item used when converting a Progress Claim into an ERPNext invoice.
Review Construction Settings during implementation before users begin generating invoices.
| DocType | Purpose |
|---|---|
| BF Bill of Quantities | Commercial baseline and BOQ lines |
| BF BOQ Item | BOQ detail row |
| BF Tender | Tender linked to BOQ and Project |
| BF Contract | Main Contract or Subcontract |
| BF Contract Submittal | Required contract documents |
| BF Document Type | Configurable submittal/document categories |
| BF Site Mobilization | Mobilization checklist and completion control |
| BF Site Mobilization Item | Mobilization detail |
| BF Mobilization Template | Standard mobilization template |
| BF Mobilization Template Task | Template detail |
| BF Mobilization Task | Mobilization task definition |
| BF Site Measurement Log | Site measurement transaction |
| BF Measurement Item | BOQ measurement row |
| BF Progress Claim | Interim progress claim / IPC |
| BF Progress Claim Item | BOQ certification detail |
| BF Progress Claim Variation | Variation certification detail |
| BF Variation Order | Contract variation |
| BF Variation Item | Variation detail |
| BF Construction Settings | Construction configuration |
ConsMS relies heavily on standard ERPNext master and transaction DocTypes.
Current references include:
- Project
- Customer
- Supplier
- Item
- UOM
- Material Request
- Material Request Item
- Purchase Order
- Purchase Order Item
- Purchase Receipt
- Purchase Receipt Item
- Purchase Invoice
- Purchase Invoice Item
- Sales Invoice
Because these are core ERPNext objects, this branch should be treated as an ERPNext-integrated Frappe application, even though required_apps is not currently enforced in hooks.py.
ERPNext-integrated Frappe application
The app technically declares itself as a Frappe package, but its operational workflows depend on ERPNext DocTypes and accounting/procurement transactions.
Production deployment should therefore assume ERPNext is required unless the code is refactored to remove these dependencies.
- Python:
>=3.10 - Packaging: modern
pyproject.toml/ Flit - App package:
consms - Project package name:
construction_ms - Module:
Construction Management - License: MIT
- Development tooling:
- Ruff
- ESLint
- Prettier
- Pyupgrade
- pre-commit
The current pyproject.toml does not declare an explicit supported Frappe version.
Before production installation, confirm compatibility with the target:
- Frappe version
- ERPNext version
- Python version
- MariaDB version
- Node version
From a Frappe Bench:
cd $PATH_TO_YOUR_BENCH
bench get-app https://github.com/Aakvatech-Limited/ConsMS.git --branch master
bench --site <site-name> install-app consms
bench --site <site-name> migrateFor production deployments, pin a tested commit or release rather than installing an unpinned moving branch.
Before using ConsMS:
- Configure Company and ERPNext accounting.
- Create Customers and Suppliers.
- Configure Projects.
- Create Items and UOMs.
- Configure the default Progress Claim invoice Item in BF Construction Settings.
- Configure BF Document Types for required contract submittals.
- Configure Mobilization Templates where applicable.
- Review Contract retention and contingency defaults.
- Validate VAT handling against local tax requirements.
- Confirm invoice integration custom fields exist.
- Test permissions for each business role.
- Validate print formats, especially IPC certification.
- Validate procurement-to-BOQ linkage before live purchasing.
Most construction DocTypes in the current repository expose broad permissions to System Manager.
This is suitable for development but is not sufficient as a final production authorization model.
Before go-live, define operational roles such as:
- Quantity Surveyor
- Contracts Manager
- Commercial Manager
- Project Manager
- Site Engineer
- Procurement User
- Procurement Manager
- Finance User
- Finance Manager
- Construction Administrator
Then assign create, write, submit, cancel and amend privileges according to segregation-of-duties requirements.
The current code includes several useful business controls:
- One active Contract per Tender
- Site Mobilization cannot submit until all tasks are completed
- Progress Claim periods cannot overlap for the same Contract
- Progress Claim date ranges must be valid
- Variation claims cannot exceed approved variation values
- BOQ amounts recalculate from quantity × rate
- Variation Order amounts recalculate from quantity × rate
- Contract contingency is calculated automatically
- High contingency values generate a warning
- Progress Claims derive quantities from submitted Site Measurement Logs
- Previous certified quantities are carried forward into later claims
| Component | Type |
|---|---|
| BF Contract Profitability | Script Report |
| BOQ Budget vs Expenditure | Script Report |
| Variation vs Budget Report | Report definition |
| Monthly Contract Awards | Dashboard Chart |
| Submittal Approval Rate | Dashboard Chart |
| Active Tenders | Number Card |
| Pending Submittals | Number Card |
| Total Awarded Contracts | Number Card |
| Total Variation Value | Number Card |
The application exposes whitelisted server-side methods supporting mapped-document and transactional workflows, including:
- BOQ → Material Request
- BOQ → Tender
- Tender → Contract
- Contract → Site Mobilization
- Contract → Variation Order
- Contract → Progress Claim
- Progress Claim measurement retrieval
- Progress Claim → Sales Invoice
- Progress Claim → Purchase Invoice
- BOQ item search/filtering
These methods are designed to be called from Frappe client-side forms.
Active application hooks currently include:
doctype_js = {
"Material Request": "public/js/material_request.js"
}The effective current hook is:
after_migrate = "consms.setup.after_migrate"override_doctype_dashboards = {
"Material Request": "consms.setup.get_material_request_dashboard"
}hooks.py currently contains two after_migrate assignments.
The later assignment overrides the earlier one.
This should be reviewed before relying on automatic creation of every intended custom field.
The active setup routine creates BOQ references on standard ERPNext procurement documents.
The repository also contains a separate consms/custom_fields.py definition for Sales Invoice fields:
- Construction Contract
- Progress Claim (IPC)
Because of the duplicate after_migrate hook assignment described above, deployments should confirm whether these fields are present on the target site.
No active scheduler events are currently configured in hooks.py.
The core application operates primarily through:
- DocType validation
- mapped document actions
- whitelisted server calls
- standard Frappe transactions
- reports
- workspace/dashboard resources
consms/patches.txt currently contains the standard pre-model-sync and post-model-sync sections but no active migration patches.
Most current setup is performed through DocType synchronization and after_migrate.
Clone/install through Bench, then enable the repository's development tooling.
cd apps/consms
pre-commit installConfigured tooling includes:
- Ruff
- ESLint
- Prettier
- Pyupgrade
Run the relevant Frappe test suite against the target framework version before merging functional changes.
ConsMS/
├── .github/
│ └── workflows/
├── README.md
├── license.txt
├── pyproject.toml
├── consms/
│ ├── hooks.py
│ ├── setup.py
│ ├── custom_fields.py
│ ├── patches.txt
│ ├── public/
│ │ └── js/
│ │ └── material_request.js
│ └── construction_management/
│ ├── doctype/
│ │ ├── bf_bill_of_quantities/
│ │ ├── bf_boq_item/
│ │ ├── bf_tender/
│ │ ├── bf_contract/
│ │ ├── bf_contract_submittal/
│ │ ├── bf_document_type/
│ │ ├── bf_site_mobilization/
│ │ ├── bf_site_mobilization_item/
│ │ ├── bf_mobilization_template/
│ │ ├── bf_mobilization_template_task/
│ │ ├── bf_mobilization_task/
│ │ ├── bf_site_measurement_log/
│ │ ├── bf_measurement_item/
│ │ ├── bf_progress_claim/
│ │ ├── bf_progress_claim_item/
│ │ ├── bf_progress_claim_variation/
│ │ ├── bf_variation_order/
│ │ ├── bf_variation_item/
│ │ └── bf_construction_settings/
│ ├── report/
│ ├── dashboard_chart/
│ ├── number_card/
│ ├── print_format/
│ └── workspace/
└── ...
| Traditional process | With ConsMS |
|---|---|
| BOQ managed in spreadsheet | BOQ stored in Frappe |
| Tender recreated manually | Tender mapped from BOQ |
| Awarded contract entered separately | Contract mapped from Tender |
| Mobilization checklist maintained externally | Mobilization tracked in dedicated DocType |
| Site measurements kept in books/spreadsheets | Measurement Log linked to BOQ |
| IPC prepared manually | Claim generated from measurements and prior claims |
| Variations managed separately | Variations linked to Contract and IPC |
| Procurement disconnected from BOQ | ERPNext procurement rows linked to BOQ items |
| Budget control calculated manually | BOQ Budget vs Expenditure report |
| Contract profitability assembled offline | Contract Profitability report |
- Create Project.
- Create BOQ.
- Add BOQ quantities and unit rates.
- Submit BOQ.
- Create Tender from BOQ.
- Award Tender and create Contract.
- Create Site Mobilization from Contract.
- Load mobilization checklist.
- Complete all mobilization tasks.
- Submit Mobilization.
- Create Material Request from BOQ.
- Carry BOQ references into purchasing transactions.
- Track commitments and expenditures against BOQ items.
- Record Site Measurement Logs.
- Select BOQ lines.
- Enter measured quantities.
- Submit measurements.
- Create Progress Claim from Contract.
- Select certification period.
- Fetch measured quantities.
- Review previous quantities.
- Review approved variations.
- Apply materials on site, retention and recoveries.
- Submit the Progress Claim.
- Generate Sales Invoice for client claim or Purchase Invoice for subcontractor claim, subject to deployment validation of the required custom fields.
- Review contract profitability and BOQ budget-versus-expenditure reports.
With appropriate implementation and controls, ConsMS can help organizations improve:
- contract traceability
- BOQ control
- procurement budget visibility
- measurement discipline
- progress certification consistency
- variation control
- retention calculation
- commercial reporting
- contract profitability visibility
- integration between site, procurement and finance teams
- auditability of construction commercial records
Implementation effort will depend on:
- complexity of BOQs
- number of active contracts
- subcontract structure
- existing ERPNext configuration
- procurement processes
- tax rules
- certification rules
- retention practices
- advance payment terms
- role and approval structure
- reporting requirements
- historical migration needs
A pilot project should be completed before migrating all live construction contracts.
For existing construction projects, consider migration of:
- Projects
- BOQs
- BOQ line identifiers
- Tenders
- Main Contracts
- Subcontracts
- Approved Variation Orders
- Previous certified quantities
- Previous certified amounts
- retention balances
- advance-payment recovery balances
- procurement commitments
- historic invoices
Opening commercial balances must be designed carefully to avoid double-counting previous certification.
The application depends on multiple ERPNext DocTypes but required_apps is not currently configured.
hooks.py assigns after_migrate twice. Only the latter assignment is effective.
Progress Claim invoice creation expects construction linkage fields. Confirm these fields exist on Sales Invoice and Purchase Invoice in the target deployment.
Many custom DocTypes primarily grant access to System Manager. Production role design is required.
Retention, VAT, advance recovery and certification formulas must be validated against:
- contract conditions
- jurisdiction
- tax treatment
- client requirements
Test the app on the intended Frappe/ERPNext release before production use.
Review reporting code for:
- permission behavior
- SQL safety
- multi-company behavior
- currency handling
- performance on large datasets
ConsMS inherits Frappe's authentication, roles and document permission model.
Production deployment should additionally review:
- who can amend BOQs
- who can submit Contracts
- who can approve Variations
- who can submit Measurements
- who can submit Progress Claims
- who can generate invoices
- who can edit rates
- who can access profitability information
- who can cancel commercial documents
Commercial construction records should use strong segregation of duties.
Before upgrading:
- Take a database and file backup.
- Review the target ConsMS commit.
- Confirm Frappe and ERPNext compatibility.
- Review schema/custom-field changes.
- Run migration on a staging site.
- Validate BOQ mappings.
- Validate Material Request and procurement links.
- Test Progress Claim calculations.
- Test invoice generation.
- Review reports.
- Test dashboards/workspace.
- Run automated and manual regression tests.
- Upgrade production only after acceptance.
Run:
bench --site <site-name> migrateThen verify the effective after_migrate hook and Custom Field records.
Confirm the target invoice DocType contains the custom linkage fields expected by the controller.
Verify:
- Contract has a BOQ
- Site Measurement Logs are submitted
- measurement dates fall within the claim period
- measurement items reference the correct BOQ lines
Every checklist row must have status Completed.
Check whether another non-cancelled Contract already references the Tender.
ConsMS is a strong candidate for organizations that want construction commercial control directly inside ERPNext and need a connected flow between:
- BOQ
- Tender
- Contract
- Procurement
- Measurement
- Variation
- Progress Claim
- Invoice
- Profitability
It is especially relevant where ERPNext is already being used for accounting, buying, selling and project management.
Before enterprise rollout, complete a functional and technical validation covering:
- contract terms
- tax rules
- user permissions
- workflows
- approval levels
- invoice mapping
- BOQ procurement controls
- performance
- reporting
- localization
Yes. The current master branch includes BOQ headers and BOQ items with automatic quantity × rate calculations.
Yes.
Yes, and the backend prevents more than one active Contract per Tender.
Yes. BF Contract supports both Main Contract and Subcontract types.
Yes. Variation Orders are linked to Contracts and are incorporated into Progress Claims.
Yes. Site Measurement Logs reference BOQ items and feed claim quantities.
Yes. The app includes cumulative measurement, retention, variations, advance recovery, previous certification, VAT and certification calculations.
The controller includes mappings for Sales Invoice and Purchase Invoice. The required custom invoice fields should be verified during deployment.
Yes. Custom fields are created on key ERPNext procurement documents and their child rows.
Yes. The BOQ Budget vs Expenditure report compares BOQ budget, Purchase Orders and Purchase Invoices.
Yes. The Contract Profitability report compares revised contract value, client billing and subcontractor costs.
Yes.
This README was prepared from the current master branch, including:
README.mdpyproject.tomllicense.txtconsms/hooks.pyconsms/setup.pyconsms/custom_fields.pyconsms/patches.txt- Construction Management workspace
- BOQ DocTypes and controller
- Tender DocType and controller
- Contract DocType and controller
- Contract Submittal structures
- Mobilization DocTypes and controller
- Site Measurement DocTypes and controller
- Progress Claim DocTypes and controller
- Variation Order DocTypes and controller
- Contract Profitability report
- BOQ Budget vs Expenditure report
- dashboard charts
- number cards
- FIDIC IPC Certificate print format
- Material Request integration
- repository automation and developer tooling
The following items should be considered before treating the app as production-hardened:
- Declare supported Frappe/ERPNext dependencies in
pyproject.toml. - Remove the duplicate
after_migrateassignment and consolidate custom-field setup. - Verify/create Contract and Progress Claim linkage fields on both Sales Invoice and Purchase Invoice.
- Add production business roles and permissions.
- Add workflow approvals for BOQ, Tender, Contract, Variation and IPC where required.
- Expand automated tests beyond basic generated DocType tests.
- Test cumulative IPC calculations using multi-period scenarios.
- Add negative tests for over-certification and overlapping periods.
- Review direct SQL reports for security and performance.
- Add multi-company and multi-currency test coverage.
- Document the intended supported Frappe/ERPNext release.
- Add screenshots and an implementation example.
This repository uses pre-commit for development quality controls.
Install it with:
cd apps/consms
pre-commit installConfigured tools include:
- Ruff
- ESLint
- Prettier
- Pyupgrade
Submit changes through a feature/fix branch and Pull Request.
Changes should include appropriate tests where business logic is modified.
MIT License.
See license.txt.
ConsMS is maintained within the Aakvatech ecosystem.